Cast-resin coils are made by winding conductors with pre-impregnated Class F insulating materials, placing the coils in moulds and vacuum-casting them with epoxy resin. The resin is typically a two-component system of resin and hardener, cured under conditions specified for that formulation. These are the core stages of the cast resin transformer manufacturing process.
Coil preparation is critical: winding accuracy, insulation placement and resin encapsulation all contribute to the transformer’s construction. Understanding how these operations fit together makes the production process easier to follow.
This guide follows the process from coil preparation and winding through resin mixing, casting, assembly and electrical testing. It explains the purpose of each stage, from the initial winding decisions to curing and final verification.
Key Takeaways
- Prepare coils with correctly placed insulation and controlled winding geometry to support the transformer’s electrical and mechanical performance.
- Understand how the core and windings are assembled so each component fits the transformer’s design.
- Mix resin and hardener according to the resin system’s requirements, then use vacuum casting and controlled curing to encapsulate the coils.
- Use electrical, mechanical and thermal tests to assess insulation, withstand performance, partial discharge, vibration and temperature behaviour.
- Follow the production sequence from coil preparation through final testing to see how each stage contributes to the finished transformer.
How Are Cast-Resin Coils Prepared?
Prepare each coil to the design specification before resin encapsulation. Winding accuracy, insulation placement and surface condition influence electrical and mechanical performance.
Cast-resin and oil-immersed transformers differ in construction, safety considerations and maintenance needs. Resin insulation avoids oil handling, while purchase cost depends on design, materials, rating and installation conditions, so neither construction is universally cheaper.
IEC 60076 is a reference for power transformers, and IEC 60076-11 is listed for cast-resin transformer testing and quality. These references identify relevant technical standards; South African project requirements should be considered separately.
Common defects include winding damage, misplaced insulation, contamination and air voids in the resin. Reduce these risks through clean handling, accurate winding, careful mould preparation and vacuum pressure casting. Follow the equipment’s operating and safety procedures at every stage.
Prepare the Transformer Winding
Wind the conductor to the specified shape and dimensions, keeping each turn aligned with the coil design. Precision winding helps the finished coil fit its core structure and supports consistent electrical performance. Inspect the conductor as you work. Avoid crossed turns, sharp bends and damage that could compromise insulation or create uneven spacing between conductors.
Apply Coil Insulation
Apply the specified insulating material between turns and across the winding as required by the design. Pre-impregnated Class F insulating materials are used for transformer windings. Keep layers even and correctly positioned, without folds, gaps or contaminants. Inspect the completed coil before moulding, since casting can enclose an insulation defect.
- Inspect the winding. Compare the coil’s shape and insulation placement with its design before moving it to the mould. Look for loose turns, damaged conductor surfaces and displaced insulation. Correct visible issues before encapsulation, when the winding remains accessible for inspection and adjustment.
- Assess the resin system’s role. Epoxy resin provides electrical insulation around the winding and mechanical support after curing. Its properties depend on the formulation and controlled processing. Fillers may improve thermal conductivity, while flame retardants may improve fire resistance. The selected system must suit the transformer design and its operating requirements.
- Prepare for casting. Place the prepared winding in its mould and keep the casting area clean. Vacuum casting helps remove air bubbles and produce a uniform, dense resin encapsulation. Trapped air or contamination can weaken the insulation system, so careful mould preparation and controlled handling matter before resin enters the coil assembly.
Place the prepared winding in its mould for casting. Electro-insulating epoxy resin is typically supplied as a two-component system of resin and hardener. The cast resin transformer manufacturing process includes winding conductors, placing them in moulds, vacuum-casting with epoxy resin and curing the resin.
After vacuum casting, cure the resin. Set the temperature and duration according to the requirements of the specific resin. This stage completes encapsulation around the winding, following mould placement and vacuum casting.
How Are Transformers Manufactured?
A cast-resin transformer transfers electrical energy through magnetic coupling between primary and secondary windings, using solid resin insulation rather than insulating oil. The cast resin transformer manufacturing process moves from core and winding preparation to alignment and assembly in a stable structure.
Prepare the Core and Windings
Prepare the magnetic core and windings to match the transformer design. Transformer cores are typically made from magnetic materials such as silicon steel, while precision-wound conductors form the coils. Check core pieces for damage and keep winding surfaces clean. Before assembly, confirm that the winding shape and insulation layers fit the core structure.
Assemble the Core and Windings
Position the prepared windings around the core as specified in the design, keeping each coil centred and aligned. Check clearances between the windings and core, as well as spacing between winding sections. Misalignment can affect the intended electrical arrangement and create mechanical stress. Secure the assembly so it remains stable during subsequent manufacturing operations.
- Match components to the design. Identify the primary and secondary windings before fitting them to the core. Their arrangement determines how electrical energy transfers between circuits. Confirm that each coil is in its intended position and its terminals remain accessible for later connections. Avoid swapping winding positions or shifting insulation during handling.
- Check the core assembly. Bring the core components together in the specified configuration. Silicon steel provides a magnetic path for transformer operation, making correct assembly important. Inspect joints and contact points for visible gaps or damage. Keep tools and debris away from the magnetic structures, where foreign material could prevent a close fit.
- Stabilise the combined structure. Secure the core and windings to prevent movement during assembly. Check that mechanical supports hold the coils without deforming them or pressing against insulation. Keep the assembly aligned through the later casting and curing stages. This stability helps preserve each component’s designed position throughout the cast resin transformer manufacturing process.
- Review the assembly before the next operation. Compare winding placement, terminal orientation and core alignment with the design. Check that insulation remains intact and that no winding has shifted under mechanical pressure. This review creates a clear handover into subsequent production stages. For project planning, explore transformer manufacturing capabilities alongside the required design and application.
Transformer windings are precision-wound, with insulation layered between turns and the winding shaped to fit the core. Check that the turns are accurately wound, the insulation is layered between them and the winding shape matches the core structure.
Keep the winding’s shape and insulation arrangement in view as it is handled and positioned. Compare the prepared winding with the intended core fit before proceeding, and correct any visible mismatch in its shape or insulation placement. This review helps ensure the core and windings come together as designed.
What Do the Main Electrical Tests Verify?
Factory tests assess whether the completed transformer meets its design requirements. Electrical, mechanical and thermal checks examine different risks, including insulation faults and heat build-up.
- Measure insulation resistance. Test the insulation between windings and between the windings and earth. This measurement can help identify moisture, contamination or damaged insulation that could create an unintended current path. Interpret readings against the test method and transformer design, not in isolation. A sound result supports further checks but does not replace dielectric testing.
- Apply a dielectric withstand test. This test applies a specified test voltage to assess whether insulation withstands electrical stress. It helps reveal weaknesses in the winding insulation or cast-resin encapsulation. The test is performed under controlled conditions, following the applicable procedure. IEC 60076-1 and IEC 60076-11 are listed among standards used for transformer quality and testing.
- Measure partial discharge. Partial discharge testing detects localised electrical activity within insulation. Such activity can indicate voids, defects or uneven insulation stress, including issues associated with resin casting. Vacuum casting helps limit air bubbles during production, while this test checks the finished insulation system. IEC 60076-11 is a listed reference for cast-resin transformer testing.
- Check mechanical integrity. Mechanical quality control can include vibration and impact testing. These checks assess whether the core, windings, supports and other structures remain stable under mechanical stress. Inspect the finished assembly for movement, loose components or visible damage. Mechanical checks complement electrical tests, since secure winding positions help preserve clearances and insulation integrity.
- Assess thermal performance. A temperature-rise test evaluates whether the transformer can operate within its specified temperature range without overheating. Heat behaviour depends on the design and cooling arrangement, so the test examines the completed unit under controlled operating conditions. IEC 60076-2 is listed for temperature-rise testing, while IEC 60076-10 is listed for sound-level measurement.
- Relate results to the production record. Review test results alongside manufacturing records, including winding preparation and resin curing. Resin begins as a liquid system before casting and becomes solid through controlled curing. If a result falls outside the acceptance criteria, investigate the relevant stage rather than relying on one test alone. IEC 60076-5 is also listed among transformer testing and quality references.
Together, these checks assess insulation resistance, dielectric strength, partial discharge, mechanical stability and thermal behaviour. Each provides distinct evidence about the finished transformer rather than a single pass-or-fail measure of quality.

Two-component resin and hardener mixing
Prepare a uniform casting compound using the resin system’s specified method. Resin and hardener proportions, filler selection, mixing and degassing all affect the finished insulation.
- Prepare the components. Identify the epoxy resin, hardener and any specified additives before mixing. Cast-resin systems typically use resin and hardener as their two principal components, in proportions set by the formulation. Keep containers and mixing equipment clean. Foreign material or an incorrect component can affect curing and the insulation’s electrical and mechanical properties.
- Measure and combine accurately. Follow the resin manufacturer’s formulation for the resin-to-hardener ratio and mixing method. Add the components in the prescribed order and blend until uniform. Avoid introducing air through vigorous stirring. The mixture must be consistent before it enters the mould, since unmixed areas can cure differently from the surrounding resin.
- Account for fillers. Epoxy formulations can include quartz flour or aluminium oxide hydrate. One test formulation contained epoxy resin with 65% quartz flour. Another contained 35% quartz flour and 30% aluminium oxide hydrate, and recorded an afterburn time of 2 seconds. These are specific test formulations, not universal production recipes.
- Consider each additive’s purpose. Fillers may improve thermal conductivity and heat dissipation, whilst flame retardants may improve fire resistance. Select additives as part of the resin system, rather than treating them as interchangeable ingredients. A separate test formulation with 65% quartz flour had an afterburn time below 10 seconds. Test outcomes apply to those formulations and conditions.
- Degas the mixed compound. Place the prepared resin under vacuum when required by the casting method. Removing entrained air helps limit bubbles and supports dense encapsulation around the windings. Maintain the specified processing conditions during degassing. The required vacuum pressure and duration depend on the resin system and its process requirements.
- Install auxiliary components before casting. Fit the terminals, supports and other components required by the design, then check their position and stability. Keep connection surfaces clean and accessible. Ensure fittings do not obstruct resin flow around the coil or create unwanted gaps. Once the mould is ready, introduce the mixed compound using the specified casting sequence.
- Coordinate mixing with the next production stage. Resin and hardener react once combined, so plan each batch around the casting operation. Do not hold mixed compound beyond its permitted processing conditions. After encapsulation, controlled oven heating cures the epoxy. Gradual cooling completes the sequence without exposing the solidifying resin to abrupt temperature changes.
Cast-resin transformer production
Production depends on controlling each transition from prepared coil to cured assembly. Vacuum casting, resin curing and gradual cooling help create a solid insulation system around the active parts.
- Prepare the mould and assembly. Position the coil assembly securely in a clean mould, with terminals and connection points correctly located. Check that mould surfaces are intact and resin can reach the intended areas. Careful preparation supports even casting and reduces the risk of gaps around winding structures.
- Set up the casting chamber. Place the mould in the vacuum chamber and arrange the equipment for controlled resin delivery. Check seals and connections before evacuation. Stable vacuum conditions help remove air from the mould and coil assembly, supporting dense encapsulation and limiting bubbles in the insulation.
- Evacuate before resin delivery. Reduce chamber pressure before introducing the prepared epoxy compound, allowing air within the mould and winding spaces to escape. Follow the sequence specified for the resin system. Introducing resin before evacuation can trap air and compromise the casting’s uniformity.
- Cast around the active parts. Feed resin into the evacuated mould in a controlled manner, allowing it to flow around the coil and core structures. Vacuum casting helps remove air and produce dense encapsulation. Monitor resin movement, especially around narrow spaces, terminals and edges where incomplete filling may be difficult to see.
- Release the vacuum gradually. Once resin has encapsulated the core and windings, gradually restore chamber pressure. Controlled release helps the resin settle through the mould without disturbing the casting. Before moving the mould to curing, inspect accessible surfaces for leakage or uneven filling.
- Cure the resin under controlled heat. Heat the chamber or oven according to the resin system’s requirements. Controlled heating initiates polymerisation, turning the liquid compound into solid insulation. Temperature and duration depend on the formulation, so do not assume one cure schedule suits every transformer or voltage design.
- Cool and complete the production sequence. Allow the casting to cool gradually after curing. Some production schedules also include post-curing at a slightly higher temperature for an extended period to further improve epoxy properties. After cooling, inspect the casting for visible defects and prepare the transformer for its specified factory tests.
For a project requiring a defined voltage design or production scope, discuss transformer production requirements.
Africa Switchgear & Transformers: Miniature Substations
Africa Switchgear & Transformers manufactures miniature substations and cast resin dry-type transformers for utility, mining and industrial applications. Turn to its transformer manufacturing capability when a project needs equipment aligned with its electrical design and operating requirements. The company manufactures transformers up to 20 MVA, giving project teams an OEM option for equipment requirements within that capacity.
Miniature substations, cast resin dry-type transformers and SF6 type switchgear address different parts of medium-voltage infrastructure. The right fit depends on the project’s system design, site conditions and equipment requirements. For a transformer or substation project, share the application and design requirements with Africa Switchgear & Transformers.
Contact Africa Switchgear & Transformers or visit africaswitchgear.co.za to discuss your project.
Turn manufacturing insight into a project decision
Use your understanding of the cast resin transformer manufacturing process to shape your project discussion. Define the operating environment, electrical requirements and how the transformer must integrate with the wider installation. These decisions help turn manufacturing details into a practical equipment specification.
For South African utility, mining and industrial projects, consider how a cast resin dry-type transformer fits alongside the required substation and switchgear. Africa Switchgear & Transformers offers Cast Resin Dry-Type Transformers, Miniature Substations and SF6 Type Switchgear. The right combination depends on the project’s design and application.
Bring your project requirements together and discuss the equipment scope with the manufacturer. A focused conversation can help clarify how transformer selection connects to the broader electrical system and its intended operating conditions. Contact Africa Switchgear & Transformers to take the next step and move your project planning forward with confidence.
Frequently Asked Questions
How Are Quality Checks Distributed Across Manufacturing?
Quality checks belong at key handovers, not only at final testing. Inspect winding geometry before moulding, confirm component positions before casting and review the cured assembly before factory tests. This sequence helps identify faults nearer to their source. For example, a displaced terminal found before casting can be corrected without disturbing finished resin encapsulation. Keep inspection records tied to the relevant production stage.
What materials and components are used to manufacture cast resin transformers?
Typical construction combines a magnetic core, conductive windings, insulation, epoxy resin and hardener. Silicon steel is a common core material, and pre-impregnated Class F materials may insulate the windings. Resin formulations can use fillers such as quartz flour or aluminium oxide hydrate, with other additives selected for properties such as thermal conductivity or fire resistance. Terminals and supports complete the assembly, with their arrangement determined by the transformer design.
How are transformer windings vacuum cast and cured with epoxy resin?
After the winding assembly is positioned in its mould, the casting chamber is evacuated and the prepared resin system is introduced. The vacuum helps remove trapped air as resin flows around the coil. Once encapsulation is complete, chamber pressure is gradually restored and controlled heating begins the cure. The resin formulation determines the required curing conditions. Gradual cooling follows, and some processes include a post-cure.
What quality control and electrical tests are required for cast resin transformers?
Test selection follows the transformer design and applicable specification. Factory checks can assess insulation resistance, dielectric withstand, partial discharge and temperature rise, alongside mechanical integrity. IEC 60076-1 and IEC 60076-11 are relevant listed references; IEC 60076-2 covers temperature-rise testing, IEC 60076-5 addresses short-circuit withstand, and IEC 60076-10 concerns sound-level measurement. Review test results together, since each examines a different aspect of performance.